Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)

  • Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
 
Length 13.581 km
Stations 10 Nos.
 

Dahisar (E) to Mira-Bhayander ( All Elevated)

1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium

Andheri (E) to CSIA extension

1. Airport Colony (elevated) and 2. CSIA (underground)

Elevated / Underground 11.386 km elevated and 2.195 km underground
Project base cost Rs. 6607 Crore (including state taxes and 7.5% p.a escalation)
Ridership :
2021 Daily Ridership - 8.47 Lakh (PHPDT- 24585)
2031 Daily Ridership – 11.12 Lakh (PHPDT- 30389)
Rolling Stock

Width : 3.20 m

Height : 3.90 m

Length : 21.84 m

Capacity

8 coach train : 2352 persons

Metro Line 7A

Elevated Viaduct

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Pier 100% Completed
4 Pier Protection 100% Completed
5 Pier Cap Casting 100% Completed
6 Pier Cap Erection 100% Completed
7 U-Girder Casting 100% Completed
8 U-Girder Erection 100% Completed
9 I-Girder Casting 100% Completed
10 I-Girder Erection 100% Completed
11 Deck Slab Casting 100% Completed
12 Parapet Wall Casting 100% Completed
13 Parapet Wall Erection 100% Completed

Elevated Station

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Monolithic Pier (Up to PL) 100% Completed
4 Portal Pier (Up to PL) 100% Completed
5 Pier Cap Casting 100% Completed
6 Pier Cap Erection 100% Completed
7 Portal Beam Casting at PL (Cast in Situ) 100% Completed
8 Tie Beam 100% Completed
9 U-Girder Casting 100% Completed
10 U-Girder Erection 100% Completed
11 Extended Pier Casting (PL–CL) 100% Completed
12 Precast Split Pi-Girder Casting 100% Completed
13 Precast Split Pi-Girder Erection 100% Completed
14 Precast Portal Beam Casting (Concourse Level) 100% Completed
15 T & L Girder Casting 66% Completed
16 T & L Girder Erection 29% Completed
17 Stitch at Portal Beam 64% Completed
18 Escalator Pit (PL to CL) 100% Completed

Elevated Ramp

Sr. No. Activity Progress
1 Elevated Ramp 95% Completed

2. Cut & Cover and UG Ramp

1. UG Ramp

Activity Progress
Hard Pile 100% Completed
Soft Pile 100% Completed
Tension Pile 100% Completed
Capping Beam 100% Completed
Excavation 100% Completed
Anchor Drilling & Grouting 100% Completed
Waler Erection 100% Completed
Anchor Stressing 100% Completed
Base Slab 84% Completed
Retaining Wall 65% Completed
Parapet Wall 18% Completed

Cut & Cover

Activity Progress
Hard Pile 100% Completed
Soft Pile 100% Completed
Micro Pile 100% Completed
Capping Beam 100% Completed
Excavation 73% Completed
Anchor Drilling & Grouting 83% Completed
Waler Erection 71% Completed
Anchor Stressing 83% Completed
Tension Pile (Casting) 26% Completed
Base Slab 6% Completed

Tunnel

Sr. No. Activity Progress
1 Tunnel Ring Segment Casting 100% Completed
2 TBM-1 (Down Line) 100% Completed
3 TBM-2 (Up Line) 100% Completed
4 NATM-1 0% Completed
5 NATM-2 0% Completed

UG CSMIA Station

Sr. No. Activity Progress
1 Secant Pile 100% Completed
2 Capping Beam (RMT) 100% Completed
3 Excavation 99.2% Completed
4 Anchor Installation & Grouting 96% Completed
5 Waler Erection 88% Completed
6 Anchor Stressing 96% Completed
7 Rock Bolt, Shotcrete & Wire Mesh 93% Completed
8 Tension Pile 100% Completed
9 Base Slab 79% Completed
10 Base Slab to Concourse Slab Wall 81% Completed
11 Column (Base Slab to Concourse Slab) 74% Completed
12 Concourse Slab 51% Completed
13 Concourse Slab to Base Slab Wall 47% Completed
14 Column (Concourse Slab to Roof Slab) 51% Completed
15 Roof Slab 44% Completed
16 Subway Base Slab 25% Completed
17 Subway-1 Wall 50% Completed
18 UPE Wall 30% Completed
19 Platform Slab 18% Completed
20 OTE Duct Casting 100% Completed

Metro Line 9

Elevated Viaduct

Sr. No. Activity Progress
1Working Pile100% Completed
2Pile Cap100% Completed
3Pier100% Completed
4Pier Cap Casting100% Completed
5Pier Cap Erection100% Completed
6U-Girder Casting99% Completed
7U-Girder Erection98% Completed
8Portal Beam Casting100% Completed
9Portal Beam Erection100% Completed
10I-Girder Casting100% Completed
11I-Girder Erection100% Completed
12Deck Slab Casting100% Completed
13Parapet Casting100% Completed
14Parapet Erection97% Completed

Elevated Station

Sr. No. Activity Progress
15Working Pile100% Completed
16Pile Cap100% Completed
17Pier (GL to CL)100% Completed
18Pier (CL to PL)97% Completed
19Pier (GL to PL)100% Completed
20Hammer Head99% Completed
21Concourse Pier Arm Casting100% Completed
22Concourse Pier Arm Erection100% Completed
23Platform Pier Arm Casting100% Completed
24Platform Pier Arm Erection96% Completed
25Portal Beam Casting (Dahisar Station)100% Completed
26Portal Beam Erection (Dahisar Station)100% Completed
27U-Girder Casting99% Completed
28U-Girder Erection97% Completed
29PI-Girder Casting100% Completed
30PI-Girder Erection96% Completed
31L-Girder Casting98% Completed
32L-Girder Erection97% Completed
33T-Girder Casting99% Completed
34T-Girder Erection97% Completed

Flyover

Sr. No. Activity Progress
35Working Pile100% Completed
36Pile Cap94% Completed
37Pier98% Completed
38Hammer Head100% Completed
39Abutment Pile100% Completed
40Abutment Pile Cap100% Completed
41Abutment Pier Cap100% Completed
42Dirt Wall100% Completed
43Flyover Pier Cap Casting95% Completed
44Flyover Pier Cap Erection100% Completed
45I-Girder Casting97% Completed
46I-Girder Erection96% Completed
47Deck Slab Casting91% Completed