Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)

  • Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
 
Length 13.581 km
Stations 10 Nos.
 

Dahisar (E) to Mira-Bhayander ( All Elevated)

1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium

Andheri (E) to CSIA extension

1. Airport Colony (elevated) and 2. CSIA (underground)

Elevated / Underground 11.386 km elevated and 2.195 km underground
Project base cost Rs. 6607 Crore (including state taxes and 7.5% p.a escalation)
Ridership :
2021 Daily Ridership - 8.47 Lakh (PHPDT- 24585)
2031 Daily Ridership – 11.12 Lakh (PHPDT- 30389)
Rolling Stock

Width : 3.20 m

Height : 3.90 m

Length : 21.84 m

Capacity

8 coach train : 2352 persons

Updates as on 14th August 2025

Elevated Viaduct
Sr. No. Name of Work Status in %
1. Pier 100% Completed
2. Pier Cap Erection 100% Completed
3. U-Girder Erection  96% Completed
4. Portal Beam Erection 100% Completed
5. I-Grider Erection 100% Completed
6. Parapet Erection 90% Completed
Elevated Station
1. Pier (GL to CL) 100% Completed
2. Pier (CL to PL) 97% Completed
3. Pier (GL to PL) 100% Completed
4. Hammer head 99% Completed
5. U-Girder Erection 97% Completed
6. PI-Girder Erection 95% Completed
7. L-Girder Erection 97% Completed
8. T-Girder Erection 97% Completed
9. Concourse Pier Arm Erection 100% Completed
10. Platform Pier arm Erection 96% Completed
11. Portal beam Erection (Dahisar Station) 100% Completed
Flyover
1. Pier 92% Completed
1. Hammer Head 100% Completed
3. Abutment Pile Cap 100% Completed
5. Dirt Wall 100% Completed
7. Flyover Pier Cap Erection 94% Completed
9. I-Girder Erection 89% Completed
10. Deck Slab Casting 75% Completed
Line _7A
Sr. No. Name of Work Status in % Against Total Scope
Elevated Viaduct
1. U-Girder Erection 100% Completed
2. I-Girder Erection 100% Completed
3. Deck Slab Casting 100% Completed
Elevated Station
1. Portal Pier (Up to PL) 100% Completed
2. Pier Cap Erection 100% Completed
3. Portal Beam Casting at PL 100% Completed
4. Tie Beam 100% Completed
5. U-Girder Erection 100% Completed
6. Casting of Extended Pier 100% Completed
7. Pi-Girder Casting 100% Completed
8. Precast Portal Beam Casting @CL 100% Completed
ELEVATED RAMP
1. Elevated Ramp 95% Completed
Tunnel
1. Tunnel Ring Segment Casting 100% Completed
2. Main Tunnel  
3. TBM-1 (Down Line) 100% Completed
4. TBM-2 (Up Line) 100% Completed
UG CSMIA Station
1. Base Slab (Sqm) 79% Completed
2. BS to CS wall (Sqm) 68% Completed
3. Column 1st Lift (BS to CS) 48% Completed
4. Column 2nd Lift (BS to CS) 48% Completed
5. Concourse Slab 44% Completed
6. CS to RS Wall 29% Completed
7. Column (CS to RS) 44% Completed
8. Roof slab 35% Completed